Project Progress Updates

Latest updates on our construction milestones

100%

Infrastructure Works

All infrastructures including access road, construction power, engineer, operator, Army and labor camps, storage facilities, mechanical workshop, diesel storage and disperse facilities were in complete status by April 2024. Civil contractors were mobilized and started tunnel work from April 1, 2024.

In Progress

Tunnel Work

Audit tunnel: 100% complete. Penstock Tunnel 60% complete, Main Headrace Tunnel: 36% complete.

In Progress

Powerhouse

Powerhouse slope Excavation completed up to El. 818.0m However the design level of the Tail pit is 788.80m. Excavation of the Foundation for Floodwall was completed for 91.0m. Concrete works of about 1080 m³ completed. Rebar works of about 60.5 MT for the flood wall were completed.

In Progress

Headworks

Excavation of Desander slope completed up to el. 985.0m however, the Bottom Design excavation level is 981.70m. Excavation for the foundation of the under sluice was completed. The Intake area is also completed except for the Cutoff wall excavation. About 600 cum concrete works with different Grades. Rebar works completed about 34.50 MT.

Final Stage

Electro Mechanical

Contract evaluation and negotiation is ongoing. It's in its final stage.

In Progress

Transmission Line

Alignment fixing and detailed survey works have been completed. The design of all types of towers is ongoing. IEE for the Transmission line is going on. Contractor and vendor selection works are under progress. Contract documents for Bid opening preparation works are ongoing.