Frequently Asked Questions
Find answers to common questions about our project
General Questions
Project Progress Updates
Latest updates on our construction milestones
Infrastructure Works
All infrastructures including access road, construction power, engineer, operator, Army and labor camps, storage facilities, mechanical workshop, diesel storage and disperse facilities were in complete status by April 2024. Civil contractors were mobilized and started tunnel work from April 1, 2024.
Tunnel Work
Audit tunnel: 100% complete. Penstock Tunnel 60% complete, Main Headrace Tunnel: 36% complete.
Powerhouse
Powerhouse slope Excavation completed up to El. 818.0m However the design level of the Tail pit is 788.80m. Excavation of the Foundation for Floodwall was completed for 91.0m. Concrete works of about 1080 m³ completed. Rebar works of about 60.5 MT for the flood wall were completed.
Headworks
Excavation of Desander slope completed up to el. 985.0m however, the Bottom Design excavation level is 981.70m. Excavation for the foundation of the under sluice was completed. The Intake area is also completed except for the Cutoff wall excavation. About 600 cum concrete works with different Grades. Rebar works completed about 34.50 MT.
Electro Mechanical
Contract evaluation and negotiation is ongoing. It's in its final stage.
Transmission Line
Alignment fixing and detailed survey works have been completed. The design of all types of towers is ongoing. IEE for the Transmission line is going on. Contractor and vendor selection works are under progress. Contract documents for Bid opening preparation works are ongoing.
Still Have Questions?
Can't find the answer you're looking for? Please reach out to our team.
Contact Us